Garland

Garland has operating capacity, and Digital Realty registered a $20 million DFW39 Phase 2 shell addition for a future fourth data hall on September 24, 2026.
Operating + expansion filedReviewed September 28, 2026

CURRENT PUBLIC SIGNAL

What we know now

Garland has operating capacity, and Digital Realty registered a $20 million DFW39 Phase 2 shell addition for a future fourth data hall on September 24, 2026.

This is a working local record. Status reflects public announcements, filings, construction reports, and operating information available on the review date—not a guarantee that every proposed phase will be built.

State permit audit: Since September 21, 2026, TCEQ has paused data-center-related permit approvals while the ERCOT and Texas Water Development Board audits proceed. A filing, registration, or local approval does not establish that every required state authorization has been issued.

PROJECT SNAPSHOT

DFW39 Phase 2

Digital Realty
Registered / January–October 2027 filing schedule

The $20 million shell addition would add a future fourth data hall. A TDLR registration is not a verified construction start.

WHAT COULD CHANGE THIS PAGE

Signals we’re watching

Data-center timelines move quickly. These are the next public signals most likely to clarify this community’s status.
  1. 01A new construction phase, lease, or energization milestone
  2. 02Hiring, vendor, or workforce-program announcements
  3. 03Utility, water, tax, or environmental reporting

KEEP THIS PAGE CURRENT

Know something happening in Garland?

Send a public filing, meeting notice, project update, job posting, vendor opportunity, or correction.
Submit an update →