CURRENT PUBLIC SIGNAL
What we know now
Garland has operating capacity, and Digital Realty registered a $20 million DFW39 Phase 2 shell addition for a future fourth data hall on September 24, 2026.
This is a working local record. Status reflects public announcements, filings, construction reports, and operating information available on the review date—not a guarantee that every proposed phase will be built.
State permit audit: Since September 21, 2026, TCEQ has paused data-center-related permit approvals while the ERCOT and Texas Water Development Board audits proceed. A filing, registration, or local approval does not establish that every required state authorization has been issued.
PROJECT SNAPSHOT
DFW39 Phase 2
Digital RealtyThe $20 million shell addition would add a future fourth data hall. A TDLR registration is not a verified construction start.